    • Architect: PBK ATX
    • Requires Design: Yes
    • Delivery Method: CMAR

Status

  • Under Construction

  • Project Update - November 2023

    The 2022 Bond included funding for classroom additions at Southwest Elementary, reducing the district’s dependence on long-term portable buildings to accommodate new students.

    This elementary addition was designed in accordance with Belton ISD’s 2022 Educational Specifications, and designs include 10 classrooms, art and music rooms, and a new gymnasium. Plans also include collaborative spaces for Professional Learning Communities (PLCs) and teacher planning.

    November 2023 Update: Construction crews have just about finished the installation of the building pads for the gym and classroom addition.  Next up will be underground utility piping, followed quickly by work on the concrete foundations.  We expect both building additions to go vertical before the end of January 2024. Overall progress remains on schedule for an August 2024 completion.