In 2017, the Big Red Community approved a bond proposal for $149.7 million to provide:

  • A new high school
  • A new elementary school
  • Addition of music classrooms and a gymnaium at Lakewood Elementary
  • Updates to the Wall Street Auditorium in downtown Belton

Cost Savings of $7.2 million will allow the district to invest in additional priority improvement projects that will directly benefit students. 

Lake Belton High School

Lake Belton High School

Projected Cost: $121.5 million - Opened Fall 2020

  • Groundbreaking on May 17, 2018
  • Opened on August 19, 2020
  • Dedication ceremony on September 30, 2020

Charter Oak Elementary School

Charter Oak Elementary

Cost: $20.3 million - Opened Fall 2019

  • Groundbreaking on January 24, 2018
  • Opened on August 19, 2019
  • Dedication ceremony on September 24, 2019

Lakewood Elementary Addition

Lakewood Elementary

Cost: $2.6 million - Completed Fall 2018

  • Groundbreaking on January 8, 2018
  • Added gym, music classrooms and bathrooms
  • Ribbon-cutting ceremony on October 12, 2018

Pittenger Fine Arts Center Updates

Pittenger Fine Arts Center

Cost: $2.2 million - Completed Fall 2018

  • Renovated 1966 facility to provide community with event and performance space
  • Renamed after longtime Board member Randy Pittenger
  • Dedication and ribbon-cutting ceremony on September 25, 2018

 