The 2022 Bond included funding for Career and Technical Education (CTE) and Fine Arts additions at Belton High School, upgrades for the existing CTE spaces, and other capital improvements and renovations.

Following the passage of the 2022 Bond, the district collaborated with stakeholders to identify program requirements. Architectural design began in the fall of 2022 and was completed by O’Connell Robertson Architects in April 2023. 

The projects include -

Fine Arts Addition:
The building design included a new band hall with ensemble and percussion and office and storage spaces for instruments, uniforms, and color guards. 

Career and Technical Education (CTE) Addition:
The building designs consist of a CTE Addition that includes classroom spaces for ROTC, AV, and Culinary Programs, portrait/broadcasting/green studio spaces, and a kitchen and cafe. 

Career and Technical Education (CTE) Renovation/Upgrades:
The designs for the existing CTE building renovations included upgrades to the construction shop, wood shop, and classrooms for agriculture and vet tech programs.

June 2025 Update: 

Band Hall Addition: All areas are in full operation.  Final completion is pending completion of a few punch list items.

CTE Building Addition: All areas are in full operation. The construction team is currently finishing up remaining punch list items.

CTE Building Renovations: Construction activity is substantially complete and crews are wrapping up the remaining punchlist items.

Interior Renovations / HVAC Updates: This portion of the project is complete.

*Black Box Renovation: Renovation work to adapt the old band hall into a Black Box performance space with an instructional classroom, a costume shop and storage spaces is nearing contractual substantial completion. Remaining construction tasks include corrections to the main entry doors to the space and installation of the permanent controller for the stage curtains.  All remaining construction activity is expected to finish before the 2025-2026 school year.