Skip To Main Content

Southwest Elementary Addition

New Southwest Elementary classroom addition
New collaborative space within the new Southwest Elementary classroom addition
New Southwest Elementary Gym
Southwest Elementary Gym
Southwest Elementary Exterior of Classroom Addition
SWES Classroom addition foundation poured
SWES clsrm adtn ready to pour
SWES elevator shaft walls in progress
SWES New fire wall almost complete at gym addition

Project Update - June 2025

The 2022 Bond included funding for classroom additions at Southwest Elementary, reducing the district’s dependence on long-term portable buildings to accommodate new students.

This elementary addition was designed following Belton ISD’s 2022 Educational Specifications, and includes ten classrooms, art and music rooms, and a new gymnasium. The addition also includes collaborative spaces for Professional Learning Communities (PLCs) and teacher planning.

June  2025 Update: The project team is working on remaining closeout requirements and a final construction audit, after which the project will be presented to the Board of Trustees with a request to accept the project as complete and issue final payment to the construction manager. The district has received an interim deductive change order reducing the approved GMP by a credit of $1,000,000. This will be presented to the School Board for approval at the June 16, 2025 regular board meeting.