Southwest Elementary Addition
Project Update - June 2025
The 2022 Bond included funding for classroom additions at Southwest Elementary, reducing the district’s dependence on long-term portable buildings to accommodate new students.
This elementary addition was designed following Belton ISD’s 2022 Educational Specifications, and includes ten classrooms, art and music rooms, and a new gymnasium. The addition also includes collaborative spaces for Professional Learning Communities (PLCs) and teacher planning.
June 2025 Update: The project team is working on remaining closeout requirements and a final construction audit, after which the project will be presented to the Board of Trustees with a request to accept the project as complete and issue final payment to the construction manager. The district has received an interim deductive change order reducing the approved GMP by a credit of $1,000,000. This will be presented to the School Board for approval at the June 16, 2025 regular board meeting.