    • Architect: PBK ATX
    • Requires Design: Yes
    • Delivery Method: CMAR

Status

  • Under Construction

  • Project Update - January 2024

    The 2022 Bond included funding for classroom additions at Southwest Elementary, reducing the district’s dependence on long-term portable buildings to accommodate new students.
     
    This elementary addition was designed following Belton ISD’s 2022 Educational Specifications, and designs include ten classrooms, art and music rooms, and a new gymnasium. Plans include collaborative spaces for Professional Learning Communities (PLCs) and teacher planning.

    January 2024 Update: Construction crews are wrapping up installing structural concrete retaining walls, foundation footings, and grade beams. Installation of the structural concrete foundations at the gym and classroom addition is expected to be completed in January 2024. Next will be the construction of the concrete tilt-wall panels at the gym addition, the installation of CMU firewalls at the connections to the existing building, and the installation of structural steel framing at the two-story classroom addition. Overall progress remains on schedule for an August 2024 completion.